Construction Progress of Compaction Sand Piles in East Artificial Island



2012-09-03
BRIDGE


                    


The Hong Kong-Zhuhai-Macao Bridge Project is pushed forward since construction of 61 compaction sand piles outside of east artificial island have been finished by July 21nd, 2012, including 21 finished by “San Hang Zhuang 6” SCP Construction Ship, 30 by “San Hang Zhuang 7” SCP Construction Ship and 10 by “Crane 10” Construction Ship.
 
Those three kinds of construction ships simultaneously begin construction in July, which increases efficiency and promotes the project. 9350 compaction sand piles have been erected till now.

Photo from http://www.hzmb.org/cn/default.asp.